Those who are planning to set up a factory, or those who have already set up a factory but wish to change their working methods or machinery, must comply with the Environmental Ordinance to Ensure the Health and Safety of Tokyo Citizens (hereinafter referred to as the ``Environmental Preservation Ordinance''). ), it is necessary to apply for factory approval (change).
When setting up a factory, please check in advance whether it complies with other laws and regulations, such as restrictions on industry and workplace area for each zone as stipulated in the Building Standards Act.
factory
(Factory definition at the end of this page)
Flow of approval application procedure
Documents required for approval application form
- "Factory Installation (Change) Approval Application Form" Form No. 7 Part 1, Part 2
- No. 7 Form Attachment 1 Part 1, Part 2, Part 3
- No. 7 Form Attachments 2 to 7 (prepared according to the type of facility and work method)
- Attached List
- Guide map (map of area within 100 meters)
- Site/building layout map (neighborhood relationship map)
- Floor plan of each floor (facility layout)
- Elevation (north, east, south, west)
- work process
- Structure diagram of installed machine (catalog, etc.)
- Rental contract (only for business premises)
- Industrial waste treatment contract
Other required documents may be required depending on the type of factory.
How to create a permit application form
- If you are writing your own manuscript, please write with a ballpoint pen or fountain pen.
- Please prepare two copies of the application form: the original and a copy. You may use copy paper for copies. A copy will be returned to you along with the issuance of the factory permit.
- Please refer to the examples for filling out and creating the application form.
Note: Regarding various notification documents, if there is an error in the written contents due to the abolishment of seals, please correct them using double lines, etc.
commission
1 In the case of factory installations: If the total floor area of the workplace is 500 square meters or less: 8,700 yen per unit.If the total floor area of the workplace is more than 500 square meters but not more than 1,000 square meters: 14,200 yen per unit Floor area of the workplace Total area exceeding 1000 square meters: 20,200 yen per item
2 For factory changes: 7,600 yen per case
When you come to the office to apply for approval
Please contact the city representative in advance and have a factory representative or person in charge come to the city office.
Note: A copy of the application form will be returned at a later date. After the review is complete, we will ask the applicant to come back to our office and return the documents.
Example
Example of factory installation permit application form (Word: 314KB)
Style
Attachment 1 (Form No. 7) Part 2 [Building use, structure, area, etc. by building] (Word: 52KB)
Attachment 1 (Form No. 7) Part 3 [Facilities such as machinery and equipment] (Word: 46KB)
Attachment 5 (Form No. 7) Part 1 [Structure of wastewater generating facilities, etc.] (Word: 49KB)
Attachment 5 (Form No. 7) Part 2 [Sewage treatment method] (Word: 67KB)
Attachment 7 (Form No. 7 related) [Structure of groundwater pumping facilities, etc.] (Word: 39KB)
Form No. 9 (Related to Article 34) [Construction Completion Notification Form] (Word: 31KB)
Form No. 12 (Article 37 related) [Factory status notification form] (Word: 38KB)
Form No. 13 (Article 38 related) [Notification of change of name, etc.] (Word: 33KB)
Form No. 14 (Article 39) [Notification of Termination] (Word: 33KB)
Form No. 15 (Article 40-related) [Notification of Succession] (Word: 34KB)
Form No. 18 (related to Article 45) [Groundwater pumping amount report] (Word: 38KB)
Attachment 1 (Form No. 18) [Groundwater pumping record (for statistics)] (Word: 52KB)
Attachment 2 (Form No. 18) [Groundwater pumping record (for each facility)] (Word: 51KB)
Form No. 19 (Article 46 related) [Accident notification form] (Word: 39KB)
Form No. 20 (Article 46) [Accident Recurrence Prevention Measures Plan] (Word: 34KB)
Form No. 22 (Article 47) [Plan for reducing smoke, etc.] (Word: 36KB)
Attachment 1 (Form No. 22) [Plan for reducing soot and smoke] (Word: 37KB)
Attachment 2 (Form No. 22) [Plan for reducing dust, harmful gases, or bad odors] (Word: 34KB)
Attachment 3 (Form No. 22) [Sewage reduction plan] (Word: 39KB)
Attachment 4 (Form No. 22) [Noise or vibration reduction plan] (Word: 31KB)
Form No. 29 (related to Article 52) [Chemical substance management method manual] (Word: 36KB)
Attached sheet (Form No. 29) [Chemical substance management method manual] (Word: 37KB)
Notification form related to soil contamination according to the Tokyo Metropolitan Environmental Protection Ordinance
The following notification forms No. 30 to No. 33-2, which are subject to Article 116 of the Tokyo Metropolitan Ordinance on Environmental Security, can be downloaded from the attached file.
Form No. 30 (Article 54-2) [Soil and Groundwater Contamination Countermeasures Plan] (Word: 52KB)
Form No. 32 (related to Article 55) [Soil contamination status investigation report] (Word: 54KB)
Form No. 33 (related to Article 56-5) [Pollution diffusion prevention plan] (Word: 53KB)
Definition of Factory
What is a factory? (Word: 35KB)
Inquiries regarding this page
Inagi City Urban Environment Development Department Living Environment Division
2111 Higashi-Naganuma, Inagi City
Phone: 042-378-2111 Fax: 042-377-4781