factory approval

Update date: April 1, 2021

Those who are planning to set up a factory, or those who have already set up a factory but wish to change their working methods or machinery, must comply with the Environmental Ordinance to Ensure the Health and Safety of Tokyo Citizens (hereinafter referred to as the ``Environmental Preservation Ordinance''). ), it is necessary to apply for factory approval (change).
When setting up a factory, please check in advance whether it complies with other laws and regulations, such as restrictions on industry and workplace area for each zone as stipulated in the Building Standards Act.

factory

(Factory definition at the end of this page)

Flow of approval application procedure

Documents required for approval application form

  1. "Factory Installation (Change) Approval Application Form" Form No. 7 Part 1, Part 2
  2. No. 7 Form Attachment 1 Part 1, Part 2, Part 3
  3. No. 7 Form Attachments 2 to 7 (prepared according to the type of facility and work method)
  4. Attached List
  5. Guide map (map of area within 100 meters)
  6. Site/building layout map (neighborhood relationship map)
  7. Floor plan of each floor (facility layout)
  8. Elevation (north, east, south, west)
  9. work process
  10. Structure diagram of installed machine (catalog, etc.)
  11. Rental contract (only for business premises)
  12. Industrial waste treatment contract

Other required documents may be required depending on the type of factory.

How to create a permit application form

  • If you are writing your own manuscript, please write with a ballpoint pen or fountain pen.
  • Please prepare two copies of the application form: the original and a copy. You may use copy paper for copies. A copy will be returned to you along with the issuance of the factory permit.
  • Please refer to the examples for filling out and creating the application form.

Note: Regarding various notification documents, if there is an error in the written contents due to the abolishment of seals, please correct them using double lines, etc.

commission

1 In the case of factory installations: If the total floor area of ​​the workplace is 500 square meters or less: 8,700 yen per unit.If the total floor area of ​​the workplace is more than 500 square meters but not more than 1,000 square meters: 14,200 yen per unit Floor area of ​​the workplace Total area exceeding 1000 square meters: 20,200 yen per item
2 For factory changes: 7,600 yen per case

When you come to the office to apply for approval

Please contact the city representative in advance and have a factory representative or person in charge come to the city office.
Note: A copy of the application form will be returned at a later date. After the review is complete, we will ask the applicant to come back to our office and return the documents.

Example

Style

Notification form related to soil contamination according to the Tokyo Metropolitan Environmental Protection Ordinance

The following notification forms No. 30 to No. 33-2, which are subject to Article 116 of the Tokyo Metropolitan Ordinance on Environmental Security, can be downloaded from the attached file.

Definition of Factory

Inquiries regarding this page

Inagi City Urban Environment Development Department Living Environment Division
2111 Higashi-Naganuma, Inagi City
Phone: 042-378-2111 Fax: 042-377-4781

Main text ends here
to the top


Below is the footer.
Inagi City's official mascot, Inagi Nashinosuke
2111 Higashinagumanuma, Inagi City, Tokyo 206-8601
Office hours: 8:30 a.m. to 5:00 p.m. Main phone: 042-378-2111 Fax: 042-377-4781
Copyright (C) Inagi City. All rights reserved.
Copyright (C)K.Okawara・Jet Inoue. All rights reserved.
End of footerReturn to top of this page