Occupation of road
Updated: April 2nd, 2021
The original purpose of roads is for the free passage of the general public, but in addition to passage, facilities such as water and sewage pipes, gas pipes, utility poles, and electric wires are installed as lifelines.
Road occupancy refers to the continuous use of a road by installing certain objects or facilities on the ground, underground, or above the road other than for the purpose of passage.
Occupying a road will impede traffic, so permission from the road manager is required.
When we occupy road which city manages based on the road law, it is necessary to receive permission of the mayor who is road manager of city road. For example, scaffolding and temporary enclosures for construction are also covered. Property that significantly interferes with traffic, which is the original purpose of the road, and private use for commercial purposes by a specific person are not permitted.
In addition, we collect private use charges based on the "collection regulations such as Inagi-shi road private use charges" on private use.
Creation of Road Occupancy Permission Application Form
Application form
Various usage fees and fees will be revised from April 1, 2020
Points to note when submitting
Precaution at the time of submission of road occupation permission application (PDF: 169KB)
Flow (PDF: 66KB) of procedures such as scaffolding
Standard Processing Period for Road Occupancy Permission
Standard processing period
8 days
Acceptance of application
We close on Tuesdays and Thursdays every week. (If it falls on a holiday, it will be the preceding weekday .)
Issuance of permit
Every week, Wednesday and Friday. (If it falls on a holiday, it will be the following weekday .)
Precautions when conducting private construction work
- Do not block general traffic. Note: If closed to traffic, ensure a safe detour that is open to everyone.
- Ensure traffic safety. Pay particular attention to the safety of children on school routes.
- If the road is excavated, restore it on the same day. Note: The same applies to division lines.
Submission of notification of start of construction<br id="3"/>Before starting construction, please submit a notification of start of construction.
Witnessing of road restoration <br id="7"/>If a road is excavated, we will ask you to maintain the affected area at the time of the main restoration. increase.
Report of completion of construction <br id="11"/>Once construction is completed, please submit a "Notification of Construction Completion".
Extension of construction period
If you need to extend the construction period due to unavoidable circumstances, please apply for the extension of the construction period in advance.
Procedures for withdrawal
If you have received permission to occupy the road, but you no longer occupy it before the start of construction, please go through the procedures for withdrawal.
About procedure when we remove private property
When you remove private use article and are going to restore road to original state, please file for road exclusive use article removal construction enforcement enforcement beforehand.
Available date and time
From 8:30 a.m. to 5:00 p.m. of open agency day
Adobe Acrobat Reader DC (formerly Adobe Reader) is required to open PDF format files.
If you don't have it, you can download it for free from Adobe.
Download Adobe Acrobat Reader DC
Inquiries about this page
Inagi City Urban Construction Department Management Section
2111 Higashi Naganuma, Inagi City, Tokyo
Phone: 042-378-2111 Fax: 042-377-4781