Roadside Excavation Enforcement Discussion
Updated: November 11, 2020
Areas adjacent to roads managed by Inagi City are designated as roadside areas. When excavating more than 50 centimeters in the roadside area, Inagi City can request prior excavation enforcement consultation for the purpose of road maintenance.
The designated roadside area is determined by the width of the road in front of the site to be excavated.
Roadside Excavation Enforcement Consultation usually takes about 10 days for document review and site confirmation, so if Inagi City requests consultation, please submit the roadside excavation enforcement agreement 10 days before the start of construction.
Scope of Submission of Roadside Excavation Enforcement Agreement
If the excavation range falls under any of the following, it will be the scope of submission of the roadside excavation enforcement agreement.
1. When excavating a designated roadside area of 50 centimeters or more and excavating deeper than the distance between the excavation location and the road boundary.
2. When the road administrator deems that there is a risk of affecting the road
3. When changing the existing ground by filling, cutting, etc.
4. When the road administrator deems it necessary
About road form and roadside designated area
1. If the width of the road in front is less than 6 meters, 1/2 of the road width from the site boundary line
2. If the front road width is 6 meters or more and less than 20 meters, 3 meters from the site boundary line
3. If the front road width is 20 meters or more, 5 meters from the site boundary line
4. 10 meters inside the bend if the center radius of the bend is less than 10 meters
5. If there is a row of trees, dense trees, or bamboo groves on the roadside, 10 meters on that side.
6. If there is a high retaining wall connected to the road, 1.5 times the height of the retaining wall
7. If there is a dangerous place such as a stone quarry connected to the road, 20 meters on that side
About procedures
1. Please submit the relevant documents to the Management Division at least 10 days before excavation.
Documents to be submitted should be written in A4 size horizontally and should be left-bound, and be prepared in two copies.
(Originals should be indexed in numerical order from the table of contents.)
Confirm and accept the submitted documents.
↓
2.On-site confirmation City conducts on-site investigation. If necessary, the applicant may be asked to be present.
↓
3.Creation of roadside excavation implementation response form As a result of the site survey and witnessing, if there is no problem with the content, etc., we will carry out the administrative procedure for the response form.
↓
4.Issuance of roadside excavation enforcement answer book Come to city hall and issue answer book in management section.
↓
5.Start of excavation work When you start excavation work, please submit a notification of start to the management section.
↓
6. Completion of excavation work When all construction work is completed, please submit a completion report to the management section after attaching construction photos.
↓
7.Attendance at completion of excavation work Upon completion of the excavation work, the city and the applicant will conduct on-site confirmation.
Roadside Excavation Enforcement Consultation Related Documents
About downloading such as application documents, please see page of roadside excavation enforcement discussion-related style .
Available date and time
From 8:30 a.m. to 5:00 p.m. of open agency day
Inquiries about this page
Inagi City Urban Construction Department Management Section
2111 Higashi Naganuma, Inagi City, Tokyo
Phone: 042-378-2111 Fax: 042-377-4781