A vehicle with a special structure or a vehicle with a special cargo that exceeds any of the "vehicle limits based on the Road Act (general limit values)" is called a "special vehicle."
If a "special vehicle" tries to pass on the road, it cannot pass without obtaining permission from the road manager.
About procedures
(1) When there is only one road administrator on the requested route If there is only one road administrator on the requested route from the departure point to the destination, apply at the window of that administrator.
If you only drive on Inagi City roads, apply to Inagi City.
(2) If the requested route crosses multiple road administrators If the requested route from the departure point to the destination crosses over multiple road administrators, apply at the window of one of the road administrators.
Note: Municipalities cannot accept applications.
Vehicle traffic authorization application
Even if the vehicle does not exceed the "vehicle limit (general limit value) based on the Road Act", there is a limit due to the relationship between the width of the road and the width of the vehicle.
Even if the above restrictions apply, if you have no choice but to pass, you need to obtain a passage authorization from the administrator of the road you are passing.
About procedures
In the case of Inagi city road, please apply at the window of the city construction department management section.
The following documents are required for the application.
(1) Vehicle traffic authorization application form 1 set (2) Route map (1/5,000 or more, showing the city road and destination) 2 copies (3) Vehicle breakdown (when applying for 2 or more vehicles at the same time) ) 2 copies (4) Copy of automobile inspection certificate 1 copy
Guidance (commentary) of vehicle traffic authorization (PDF: 191KB)
Pedestrian-only road, etc. Traffic permission application
If you have no choice but to travel on a part of a pedestrian-only road that is not normally used by vehicles, you must obtain a permit.
About procedures
In the case of Inagi city road, please apply at the window of the city construction department management section.
The following documents are required for the application.
(1) Pedestrian road permission application 2 copies (2) Route map (1/5,000 or more) 2 copies (3) Plan view (1/1,000 or more) 2 copies (4) Vehicle breakdown (2 or more vehicles) at the same time) 2 copies (5) Copy of automobile inspection certificate 1 copy
Standard processing period
7 business days
Application form
Application documents related to road traffic
Available date and time
From 8:30 a.m. to 5:00 p.m. of open agency day
Adobe Acrobat Reader DC (formerly Adobe Reader) is required to open PDF format files.
If you don't have it, you can download it for free from Adobe.
Download Adobe Acrobat Reader DC
Inquiries about this page
Inagi City Urban Construction Department Management Section
2111 Higashi Naganuma, Inagi City, Tokyo
Phone: 042-378-2111 Fax: 042-377-4781