Roadside Excavation Implementation Consultation
Areas adjacent to roads managed by Inagi City are designated as "roadside areas." If excavation of 50 centimeters or more is planned within the roadside area, Inagi City may require prior consultation for excavation works for the purpose of road preservation.
The designation of roadside areas is determined by the width of the road in front of the excavation site, and even outside the designated roadside area, submission of a consultation document may be required.
Roadside excavation consultation typically takes about 10 days for document review and on-site confirmation, so if Inagi City requests consultation, please submit the roadside excavation consultation document at least 10 days before starting construction or other activities.
Regarding the Scope of Submission for the Roadside Excavation Implementation Agreement
If the excavation range falls under any of the following, it will be subject to the submission of the roadside excavation implementation agreement.
- If excavating more than 50 centimeters in designated roadside areas and deeper than the distance from the excavation site to the road boundary
- If the road manager recognizes that there is a risk of affecting the road
- When changing the existing ground due to embankment, excavation, etc.
- When deemed necessary by the road administrator
About Road Types and Designated Areas Along the Road
- If the width of the road in front is less than 6 meters, it is half the width of the road from the property boundary.
- If the width of the road in front is between 6 meters and 20 meters, it should be 3 meters from the property boundary.
- If the width of the road in front is 20 meters or more, it is 5 meters from the property boundary line.
- If the center radius of a road curve is less than 10 meters, it is 10 meters inside the curve.
- If there are rows of trees, dense trees, or bamboo groves along the roadside, 10 meters on that side
- If there is a high retaining wall connected to the road, it should be 1.5 times the height of the wall.
- If there are dangerous places such as quarries connected to the road, 20 meters on that side
About the Procedure
- Please submit the relevant documents to the Management Division at least 10 days before the excavation.
Please prepare the submitted documents in A4 landscape format, bound on the left, in two copies.
(Please index the main document in the order of the table of contents.)
The submitted documents will be reviewed and accepted. - Site Confirmation
The city will conduct a site survey. If necessary, we may ask the applicant to be present during this process. - Creation of Roadside Excavation Implementation Response Document
If there are no issues with the content, based on the results of the site survey and attendance, we will proceed with the administrative procedures for the response document. - Issuance of Roadside Excavation Implementation Response Document
You can come to City Hall to receive the response document at the Management Division. - Start of Excavation Work
Please submit a notification of commencement to the Management Division when starting excavation work. - Completion of Excavation Work
Once all work is completed, please submit the completion report along with construction photos to the Management Division. - Confirmation of Completion of Excavation Work
The city and the applicant will conduct a site inspection to confirm the completion of the excavation work.
Submitted Documents
Roadside Excavation Implementation Agreement (2 copies)
1. Roadside Excavation Implementation Agreement
2. Power of Attorney
3. Affidavit
4. Summary of Building Specifications
5. Excavation Work Specifications
6. Floor Plan (Site Plan)
7. Retaining Wall Plan
8. Retaining Wall Calculation
9. Current Condition Photos
10. Schedule
11. Building Confirmation Notification Copy
12. Reference Point Detailed Diagram
13. Guide Map
14. Others
Note: Items 2 to 14 can be in any format.
Notice of Commencement (2 copies)
Completion Notification (2 copies)
Available Procedure Dates
Open on weekdays from 8:30 AM to 5:00 PM
Please let us know your feedback on how to make our website better.
Inquiries about this page
Inagi City Department of Urban Development Management Division
2111 Higashi-Naganuma, Inagi City, Tokyo 206-8601
Phone number: 042-378-2111 Fax number: 042-377-4781
Contact Inagi City Department of Urban Development Management Division