How long does it take to process the guidelines for residential land development, etc.?

Updated: September 4, 2013

As for the standard processing time, it takes about 4 to 6 weeks after receiving the application for pre-review, and about 2 to 3 weeks after receiving the application for approval.
Note: The above period is the standard period when there are no missing documents or errors in the submitted documents. 

Inquiries regarding this page

Inagi City Urban Construction Department Town Development Planning Division
2111 Higashi-Naganuma, Inagi-shi, Tokyo
Phone: 042-378-2111 Fax: 042-378-9719

End of main text
to the top


Below is the footer.
Inagi City official character Inagi Shinanosuke
2111 Higashinagumanuma, Inagi City, Tokyo 206-8601
Opening hours: 8:30am to 5:00pm Main phone number: 042-378-2111 Fax number: 042-377-4781
Copyright (C) Inagi City. All rights reserved.
Copyright (C)K.Okawara・Jet Inoue. All rights reserved.
End of footerReturn to top of this page